Brockton Clean Energy

Energy Facilities Siting Board – Final Decision

 

EFSB DecisionEnergy Facilities Siting Board – Final Decision (APPROVED)

 Pursuant to G.L. c. 164, § 69J¼, the Energy Facilities Siting Board (Siting Board‖ or “EFSB”) hereby APPROVES, subject to the conditions set forth below, the petition of Brockton Power Company LLC (”Brockton Power”) for approval to construct a 350 megawatt (MW) combined-cycle, dual fuel (natural gas and ultra-low sulfur diesel oil (ULSD)) electric generating facility (the “proposed facility” or “project”) in Brockton, Massachusetts. Pursuant to G.L. c. 164, § 72, the Siting Board also APPROVES the petition of Brockton Power to construct an electricity transmission line connecting the proposed facility to the regional transmission grid.

  • Share/Bookmark

Share your comments

Tell us what you're thinking...
and if you want a picture to show with your comment, go get a gravatar!

Brockton Clean Energy